Overview
Street maintenance is one of the largest and most expensive responsibilities of Township government. White Bear Township is continuing to make improvements to their Pavement Management Program to preserve the Town’s 42.9 miles of local roads, provide for the safe and efficient travel of its citizens, retain property values, keep the city attractive and desirable, and minimize costs to the property owners and taxpayers for the Town.
Project Information
White Bear Township is considering street improvements for the following streets:
- Greenhaven Drive
- Gilfillan Lane
- Moon Lake Circle
- Crescent Curve
- Meadowlands Drive
- Birch Bend Lane
- Birch Lake Blvd N
The White Bear Township Pavement Management Program identified these streets for possible improvement in 2022. On August 15, 2022 the White Bear Township Town Board ordered the preparation of a feasibility report for the Township’s 2023 street improvements. Below will be a map showing the street improvement areas studied in the feasibility report.
Project Updates:
Thursday, October 16, 2023 - Site reviews will take place following the weekend's rain events.
Wednesday, October 11, 2023 - Punch list item review will take place.
Tuesday, October 10, 2023 - Punch list item review will take place.
Monday, October 9, 2023 - Site reviews will take place following weekend rain events.
Friday, October 6, 2023 - The project area, including restoration, will be reviewed following recent rain events.
Thursday, October 5, 2023 - No work is scheduled for today.
Wednesday, October 4, 2023 - Site condition reviews will take place due to yesterday's rain events.
Tuesday, October 3, 2023 - Restoration areas will be reviewed following last weekend’s rain events.
Thursday, September 29, 2023 - Site condition reviews will take place due to continued rain events.
Wednesday, September 27, 2023 - Site reviews will take place following the rain events.
Tuesday, September 26, 2023 - More site condition review will take place due to continuing rain events.
Monday, September 25, 2023 - Contractor is reviewing site conditions following the weekend’s rain events.
Friday, September 22, 2023 - Restoration of the project area will be reviewed.
Thursday, September 21, 2023 - Punch list and restoration review will take place throughout the project area.
Wednesday, September 20, 2023 - Punch list review will take place throughout the project area.
Tuesday, September 19, 2023 - Storm sewer review will take place throughout the project area.
Monday, September 18, 2023 - Contractor is reviewing restoration throughout the project area.
Friday, September 15, 2023 - Contractor is working on removing and replacing a storm sewer apron in the pond on Meadowlands Drive.
Thursday, September 14, 2023 - The storm catch basin erosion bags have been removed from the project area.
Wednesday, September 13, 2023 - Site reviews will take place in preparation for storm sewer improvements.
Tuesday, September 12, 2023 - Contractor will be reviewing the project site in preparation for punch list items to be completed.
Monday, September 11, 2023 - Site reviews will take place in preparation for storm sewer improvements.
Friday, September 8, 2023 - Preparation is taking place for storm sewer improvements.
Thursday, September 7, 2023 - Preparation is taking place for storm sewer improvements.
Wednesday, September 6, 2023 - No work is scheduled to take place on site today.
Tuesday, September 5, 2023 - Reviews will take place throughout project area.
Friday, September 1, 2023 - Reviews will take place of various items throughout the project site.
Thursday, August 31, 2023 - Reviews will take place of various items throughout the project site.
Wednesday, August 30, 2023 - No work is scheduled to take place today.
Tuesday, August 29, 2023 - No work is scheduled to take place today.
Monday, August 28, 2023 - No work is scheduled to take place today.
Friday, August 25, 2023 - No work is scheduled to take place today.
Thursday, August 24, 2023 - The contractor completed sod and seed restoration of a few remaining areas yesterday. No other work is scheduled to take place today.
Wednesday, August 23, 2023 - Site reviews will take place throughout project area. No other work is scheduled to take place today.
Tuesday, August 22, 2023 - There is no work scheduled to take place today.
Monday, August 21, 2023 - There is no work scheduled to take place today.
Friday, August 18, 2023 - Yesterday the contractor began working on replenishing landscape rock between driveways where impacted. The contractor plans on finishing this activity today.
Thursday, August 17, 2023 - No work will take place today.
Wednesday, August 16, 2023 - No work will be performed today.
Tuesday, August 15, 2023 - Miscellaneous tasks will be completed throughout the project site. Site reviews will continue to take place.
Monday, August 14, 2023 - Site review and miscellaneous tasks will be completed throughout the project site.
Friday, August 11, 2023 -Site review and miscellaneous tasks will be completed throughout the project site.
Thursday, August 10, 2023 - Miscellaneous tasks will be performed throughout the project area. Site reviews will continue to take place.
Wednesday, August 9, 2023 - All sodding for the project has been completed. Site reviews will continue to take place.
Tuesday, August 8, 2023 - Contractor is preparing the site to continue restoration work.
Monday, August 7, 2023 - Miscellaneous tasks are to be performed throughout the project area.
Friday, August 4, 2023 - Sodding crews are on site and working on restoration.
Thursday, August 3, 2023 - Contractor is installing sod throughout the project area. They are beginning on Gilfillan Lane and will work east throughout the project site.
Wednesday, August 2, 2023 - Sodding and other restoration is scheduled to take place later this week.
Tuesday, August 1, 2023 - Contractor is performing site cleanup and miscellaneous tasks throughout the project area.
Monday, July 31, 2023 - Sodding and other restoration is scheduled to take place later in the week.
Friday, July 28, 2023 - The contractor will complete paving North Birch Lake Blvd. No sod was cut this week due to high temperatures.
Thursday, July 27, 2023 - Contractor is milling North Birch Lake Blvd. other site cleanup and miscellaneous tasks are taking place throughout project area.
Wednesday, July 26, 2023 - The contractor is working on site cleanup and other miscellaneous tasks for the project area.
Tuesday, July 25, 2023 - The contractor is working on site cleanup and other miscellaneous tasks for the project area.
Monday, July 24, 2023 - The contractor is working on site cleanup and other miscellaneous tasks for the project area.
Friday, July 21, 2023 - Contractor will be installing sod for yard restoration. They will continue to work on Gilfillan Lane and work from west to east throughout the project area.
Thursday, July 20, 2023 - Contractor will be performing restoration this afternoon. Sod will begin to be installed on Gilfillan Lane and they will work moving west to east. Seeding will take place at the ponds located on Greenhaven Drive and Meadowlands Drive. Clearing of brush will take place at the pond on Meadowlands Drive.
Thursday, July 20, 2023 - Storm sewer cleaning is taking placing on Moon Lake Circle and Crescent Curve. Other miscellaneous tasks are being completed throughout project area.
Wednesday, July 19, 2023 - Contractor has completed road striping on Meadowlands Drive, Birch Bend Lane, and Greenhaven Drive. Contractor will be performing site cleanup throughout project area. Other miscellaneous tasks will be completed by the contractor.
Tuesday, July 18, 2023 - Contractor is performing cleaning around the project area. Striping is being set up for Meadowlands Drive and Birch Bend lane and will take place tonight after business close.
Monday, July 17, 2023 - Contractor is performing site cleanup and miscellaneous activities throughout the project area.
Thursday, July 13, 2023 - The contractor is working on cleaning and concreting utility structures starting on North Birch Lake Boulevard and working towards the west. Other miscellaneous tasks are being performed throughout the project areas.
Wednesday, July 12, 2023 - Pond and storm structure cleaning will take place on Greenhaven Drive and Meadowlands Drive. Other miscellaneous activities will take place throughout the project area.
Tuesday, July 11, 2023 - Contractor will be performing miscellaneous activities throughout the project site today.
Monday, July 10, 2023 - Contractor will be performing miscellaneous activities throughout the project site today.
Friday, July 7, 2023 @ 1:10 pm - The contractor is working on installing sod on Greenhaven Drive from Crescent Curve going west.
Friday, July 7, 2023 - The contractor will be paving tomorrow (July 7) on Meadowlands Drive, Birch Bend Lane, and Greenhaven Drive.
Thursday, July 6, 2023 - The contractor is milling Greenhaven Drive from Crescent Curve to Allendale Drive. Once completed they will mill Meadowlands Drive and Birch Bend Lane. Black dirt for boulevard restoration is being prepped on Meadowlands Drive and Birch Bend Lane. Contractor is working on yard restoration on Greenhaven Drive, Gilfillan Lane, Crescent Curve, and Moon Lake Circle.
Wednesday, July 5, 2023 - The contractor is working on patching on Greenhaven drive near the church entrances and Meadowlands Drive. The contractor will begin installing sod today.
Friday, June 30, 2023 - Contractor is working on Greenhaven Drive structures. Contractor is patching the pavement on Greenhaven Drive and gravel on Meadowlands. No work is scheduled for Monday or Tuesday (Holiday).
Thursday, June 29, 2023 - Contractor is working on Greenhaven Drive structures and boulevards. Contractor will work on one structure on Moon Lake Circle. Contractor will be performing road activities on Meadowlands Drive.
Wednesday, June 28, 2023 - Contractor is paving Moon Lake Circle this morning and then the first lift on Greenhaven Drive west of Crescent Curve. Contractor is pouring concrete on Meadowlands Drive. Contractor is working on restoration on Meadowlands east of Weston Woods.
Tuesday, June 27, 2023 - Contractor first milling Crescent Curve and then Gilfillan Lane. Contractor will mill Moon Lake Circle in the afternoon. Contractor will pave Crescent Curve and Gilfillan Lane in the second half of the day. Contractor will work on gravel on Green haven Drive.
Monday, June 26, 2023 @ 3:00 pm - Contractor is performing bituminous patching on Greenhaven Drive today.
Monday, June 26, 2023 @ 1:00 pm - Contractor will mill Gilfillan Lane, Crescent Curve and Moon Lake Circle Tuesday. Contractor will pave Gilfillan Lane and Crescent Curve Tuesday afternoon. Please move cars out to Greenhaven Drive if you need them Tuesday.
Monday, June 26, 2023 - Reclaiming the bituminous road is occurring on the west end of Greenhaven Drive. Pond excavation continuing along Meadowlands Drive.
Thursday, June 22, 2023 - Contractor is prepping in front of curb and driveways for patching. Patching is taking place on Moon Lake Circle and Greenhaven Drive. Black dirt is being installed on Greenhaven Drive, Moon Lake Circle, and Crescent Curve.
Wednesday, June 21, 2023 - Iron and castings for utility structures are being raised on Greenhaven Drive and Meadowlands Drive. Black dirt is being installed on Crescent Curve, Greenhaven Drive, and Moon Lake Circle. Concrete is being poured on Meadowlands Drive.
Tuesday, June 20, 2023 - Contractor is raising iron and castings for utility structures on Moon Lake Circle and Greenhaven Drive. Concrete is being poured on Meadowlands Drive and Birch Bend Lane. Black dirt is being installed on Moon Lake Circle, Crescent Curve, and Gilfillan Lane.
Monday, June 19, 2023 - The contractor is raising iron and castings for utility structures on Greenhaven Drive and Moon Lake Circle. Bituminous patching for curb will be completed this afternoon on Moon Lake Circle and Greenhaven Drive.
Friday, June 16, 2023 - Removals are taking place on Meadowlands Drive and Birch Bend Lane. Storm sewer work is being completed on Meadowlands Drive. Bituminous patching will be completed on Crescent Curve. The contractor is prepping for bituminous patching in front of concrete curb on Greenhaven Drive and Moon Lake Circle. Please note the contractor will be working on Saturday. The Saturday work will consist of prepping for bituminous patching on Greenhaven Drive and Moon Lake Circle.
Thursday, June 15, 2023 - Storm sewer is being installed on Meadowlands Drive. Deteriorated curb and sidewalk removals are taking place on Meadowlands Drive and Birch Bend Lane. Patching for curb will take place this afternoon on Crescent Curve.
Wednesday, June 14, 2023 - Concrete sidewalk is being poured on Greenhaven Drive and Crescent Curve. Deteriorated curb and sidewalk is being removed on Meadowlands Drive. Storm sewer is being installed on Meadowlands Drive. Bituminous patching for curb will be completed on Gilfillan Lane beginning this afternoon.
Tuesday, June 13, 2023 - Sidewalk removals are taking place on Greenhaven Drive.
Monday, June 12, 2023 - Removals are taking place on Greenhaven for deteriorated sidewalk. Iron and castings for utility structures will begin to be raised on Moon Lake Circle.
Friday, June 9, 2023 - Concrete is being poured on Greenhaven Drive. Deteriorated sidewalk is being removed on Greenhaven Drive. Castings and iron from utility structures is being adjusted on Greenhaven Drive, Gilfillan Lane, and Crescent Curve.
Thursday, June 8, 2023 - Concrete is being poured on Moon Lake Circle and Greenhaven Drive. Removals are taking place on Greenhaven Drive. Structure iron and castings are being adjusted on Greenhaven Drive and Gilfillan Lane. Tree removals will be completed near storm ponds and outlets.
Wednesday, June 7, 2023 - Concrete will be poured on Greenhaven Drive, Gilfillan Lane, and Crescent Curve. Curb Removals will take place on Greenhaven Drive and Moon Lake Circle. Tree removals will take place in a few spots around storm ponds and storm pond outlets.
Tuesday, June 6, 2023 - Removals are taking place on Moon Lake Circle and Greenhaven Drive. Concrete curb is being poured on Gilfillan Lane, Greenhaven Drive, and Crescent Curve.
Monday, June 5, 2023 - Removals are taking place on Moon Lake Circle and Greenhaven Drive. Concrete curb work is scheduled to take place tomorrow, June 6th beginning on Gilfillan Lane. This schedule is weather dependent and may change.
Friday, June 2, 2023 - Removals are taking place on Greenhaven Drive, Crescent Curve, and Moon Lake Circle. Bituminous patching in front of concrete curb will take place on North Birch Lake Boulevard in the afternoon. These activities are weather dependent.
Thursday, June 1, 2023 - Removals are taking place on Greenhaven Drive, Crescent Curve, and Moon Lake Circle. Bituminous patching in front of concrete curb will take place on North Birch Lake Boulevard this afternoon.
Wednesday, May 31, 2023 - Curb and sidewalk removals are taking place on Greenhaven Drive and Crescent Curve.
Tuesday, May 30, 2023 - Curb and driveway removals are taking placing on Gilfillan Lane, Greenhaven Drive, and Crescent Curve.
Friday, May 26, 2023 - The contractor is performing site cleanup and sweeping on North Birch Lake Boulevard, Greenhaven Drive, and Gilfillan Lane in preparation for the weekend.
Thursday, May 25, 2023 - Concrete curb will be poured on Greenhaven Drive. Curb removals will take place on Greenhaven Drive, Crescent Curve and Gilfillan Lane.
Wednesday, May 24, 2023 - Concrete is being poured on North Birch Lake Boulevard. Removals for curb and sidewalk is taking place on Greenhaven Drive.
Tuesday, May 23, 2023 - The contractor is continuing curb and sidewalk removals. They are starting on North Birch Lake Boulevard this morning and once complete will be moving to Greenhaven Drive at Highway 96 and work east. New concrete will be poured beginning tomorrow May 24th.
Monday, May 22, 2023 - Contractor is beginning to remove deteriorated concrete curb and gutter and sidewalk. They will start on North Birch Lake Boulevard and then move to Greenhaven Drive and work east from Highway 96 towards Allendale.
Preliminary Project Schedule
Adopt Assessments - Special Assessment Policy | Monday, October 16, 2023 |
Assessment Hearing | Monday, October 16, 2023 |
Authorize Amount to be Assessed | |
Construction Completed | |
Construction Update Flyer Mailed | May 18, 2023 |
Award Contract - Projected Awarded Flyer | May 1, 2023 |
Bid Opening | April 26, 2023 starting at @ 9:00am |
Authorize Advertisement for Bid | April 3, 2023 |
Accept Plans & Specifications | April 3, 2023 |
Authorize Preparation of Plans & Specifications | January 18, 2023 |
Order Improvements | January 18, 2023 |
Open House at Heritage Hall (4200 Otter Lake Road) | March 27, 2023 @ 7:00 pm |
Public Hearing | January 18, 2023 @ 7:00 pm |
Call for Public Hearing | December 19, 2022 |
Open House at Heritage Hall (4200 Otter Lake Road) or online: Teams Meeting Link | January 11, 2023@ 7:00 pm |
Accept Feasibility Report | December 19, 2022 |
Project Letter, Questionnaire & Brochure Mailed to Residents | October 4, 2022 |
Authorize Preparation of Feasibility Report | August 15, 2022 |
-
Larry Poppler
Town Engineer, TKDAPhone: 952-292-1098
-
Jim Studenski
Town Engineer, TKDA