- Home
- Township Government
- Departments
- Public Works
- Engineering
- Construction / Improvement Projects
- 2021 & 2022 Street Improvements
Create an Account - Increase your productivity, customize your experience, and engage in information you care about.
The SE Area Phase 2 & 3 Virtual Neighborhood Meeting is scheduled for January 27th at 6:00 pm.
Join on your computer or mobile app:
Click here to join the meeting
Or call in (audio only)
+1 651-300-3371, United States, St. Paul
Phone Conference ID: 979 866 996#
White Bear Township is considering street improvements for the following streets:
The White Bear Township Pavement Management Program identified these streets for possible improvement in 2021 and 2022. On November 2, 2020, the White Bear Township Town Board ordered the preparation of a feasibility report for the Township’s 2021 / 2022 street improvements. Below is a map showing the street improvement areas studied in the feasibility report.
Adopt Assessments | |
Assessment Hearing | |
Authorize Amount to be Assessed | |
Construction Completed | |
Construction Begins | |
Award Contract | |
Bid Opening | |
Authorize Advertisement for Bid | |
Accept Plans & Specifications | |
Neighborhood Informational Meeting | |
Authorize Preparation of Plans & Specifications | |
Order Improvements | |
Public Hearing | |
Neighborhood Informational Meeting | |
Call for Public Hearing | |
Accept Feasibility Report | January 4, 2021 |
Neighborhood Informational Meeting - Virtual Or call in (audio only) 651-300-3371 Phone Conference ID 425-467-615# Presentation Slides | December 14, 2020 @ 6:00 pm - 7:30 pm |
Project Letter, Questionnaire & Brochure Mailed to Residents | December 2, 2020 |
Authorize Preparation of Feasibility Report | November 2, 2020 |