Gilfillan Area Street Improvements

Overview
Street maintenance is one of the largest and most expensive responsibilities of Township government. White Bear Township is continuing to make improvements to their Pavement Management Program to preserve the Town’s 42.9 miles of local roads, provide for the safe and efficient travel of its citizens, retain property values, keep the city attractive and desirable, and minimize costs to the property owners and taxpayers for the Town. 

Project Information

White Bear Township is considering street improvements for the following streets: 

  • Greenhaven Drive
  • Gilfillan Lane
  • Moon Lake Circle
  • Crescent Curve
  • Meadowlands Drive
  • Birch Bend Lane
  • Birch Lake Blvd N

The White Bear Township Pavement Management Program identified these streets for possible improvement in 2022. On August 15, 2022 the White Bear Township Town Board ordered the preparation of a feasibility report for the Township’s 2023 street improvements. Below will be a map showing the street improvement areas studied in the feasibility report.

Image does not exist

Project Updates:

Preliminary Project Schedule

Adopt Assessments
Assessment Hearing
Authorize Amount to be Assessed
Construction Completed
Construction Update Flyer Mailed

Award Contract - Project Awarded Flyer
Bid Opening
Authorize Advertisement for Bid
Accept Plans & Specifications
Authorize Preparation of Plans & Specifications
Order Improvements
Public Hearing
January 18, 2023 @ 7:00 pm
Call for Public HearingDecember 19, 2022
Open House at Heritage Hall (4200 Otter Lake Road) or online: Teams Meeting LinkJanuary 11, 2023@ 7:00 pm
Accept Feasibility Report 
December 19, 2022
Project Letter, Questionnaire & Brochure Mailed to ResidentsOctober 4, 2022
Authorize Preparation of Feasibility ReportAugust 15, 2022