Mallard Ponds Area Street Improvements

Overview

Street maintenance is one of the largest and most expensive responsibilities of Township government. White Bear Township is continuing to make improvements to their Pavement Management Program to preserve the Town’s 42.9 miles of local roads, provide for the safe and efficient travel of its citizens, retain property values, keep the city attractive and desirable, and minimize costs to the property owners and taxpayers for the Town. 

Project Information

On September 18, 2023, the White Bear Township Town Board ordered the preparation of a feasibility report for the Mallard Ponds Area Street Improvements. The street improvement areas are listed below:

  • Mallard Ponds Dr (from Portland Ave to Sandterra Cir)
  • Blue Bill Cir (from Mallard Ponds Dr to Culdesac)
  • Sandterra Cir (from Pintail Ln to Culdesac)
  • Pintail Ln (from Mallard Ponds Dr to Culdesac)
  • Mallard Ponds Blvd (from Mallard Ponds Dr to Portland Ave)
  • Red Pine Blvd (from County Rd J to Culdesac)
  • Bayberry Dr (from Red Pine Blvd to Red Pine Blvd)
  • Polar Bear Ln (from Bayberry Dr to Culdesac)
  • Norway Pine Dr (from Bayberry Dr to Culdesac)
  • Norway Pine Ct (from Norway Pine Dr to Culdesac)
Mallard Ponds - Feasibility Map

Project Updates:

Preliminary Project Schedule

Adopt Assessments - Special Assessment Policy
Assessment Hearing
Authorize Amount to be Assessed
Construction Completed
Construction Update Flyer Mailed

Award Contract - Projected Awarded Flyer
Bid Opening
Authorize Advertisement for Bid
Accept Plans & Specifications
Authorize Preparation of Plans & Specifications
Order Improvements
Open House at Heritage Hall (4200 Otter Lake Road)
March 2024
Neighborhood Informational Meeting / Public Hearing
January 2024
Call for Public HearingJanuary 2024
Accept Feasibility ReportDecember 2023
Neighborhood MeetingNovember 13, 2023
Project Letter, Questionnaire & Brochure Mailed to ResidentsNovember 1, 2023
Authorize Preparation of Feasibility ReportSeptember 18, 2023